GNR Building update-June 2020
Foundation and under slab works are proceeding well. Building platform 80% was completed. Foundations was poured, blockwork was completed. Will start rib raft slab and keystone wall, fence in the next 14 days.



Foundation and under slab works are proceeding well. Building platform 80% was completed. Foundations was poured, blockwork was completed. Will start rib raft slab and keystone wall, fence in the next 14 days.